Lake Dallas Road Projects

The projects listed below are collaborative efforts supported by various government funding sources, including Denton County, the City of Lake Dallas, the Town of Hickory Creek, and the City of Corinth, reflecting the geographic locations of each respective project.

Process/Phases for Roads

  1. Design Phase
  2. Bid Letting
  3. Construction

Hundley and Shady Shores (Swisher to Main)

Bid Under Review 12/3/2025

Key Project Milestones:

  • Monday, August 18 – Construction Plans Completed and distributed to Franchise Utilities
  • Monday, September 1 – Schedule of Values Completed
  • Monday, September 15 – Final Construction Bid Documents Completed
  • Wednesday, October 1 – Advertisement for Bid Issued
  • Friday, October 31 – Bid Submittal Deadline
  • Monday, November 3 – Bid Evaluation
  • Q1 2026 – Anticipated Construction Start

Kindly check back as the projects progress. This page will be updated accordingly.

Street From To Cost Phase Status Anticipated 100% Plans
Shady Shores Road Swisher Road Main Street $8,720,000 Design 100% September 2025
Shady Shores Road Swisher Road Dobbs Road $4,557,000 Design 30% January 2026
Shady Shores Road Bridge Work Swisher Road Dobbs Road
Design 90% June 2025
Hundley Drive Lake Dallas Drive East End at Marina/Park $9,700,000 Design 100% September 2025
Dobbs Road Berry Lane Shady Shores Road $6,400,000 Design 30%
Carlisle Drive Lake Dallas Drive Main Street $3,186,000 Design 60%  

Swisher Road To Dobbs Road

05 May 2025 P3TF Report

Hundley Drive and Shady Shores Road Intersection

Lake Dallas LA Sketch 2

Looking Down Shady Shores Road from Main Street

Lake Dallas LA Sketch 1